(a) Projects of the armed forces
Residential building construction project in Buhaira Governorate
Project duration: 11 months
Number of floors: 6 floors
Number of apartments: - 24 apartments
Apartment area: - 85 square meters
Delivery: The project has been delivered primary and final
Number of floors: 6 floors
Number of apartments: - 24 apartments
Apartment area: - 85 square meters
Delivery: The project has been delivered primary and final
Construction of 5 residential buildings in Highstep, second phase
Duration: 6 months.
Finishing: fully finished.
Number of floors: 7 floors.
Number of apartments: 28 apartments.
Apartment area: 130 square meters.
Delivery: The project has been delivered primary and final.
Finishing: fully finished.
Number of floors: 7 floors.
Number of apartments: 28 apartments.
Apartment area: 130 square meters.
Delivery: The project has been delivered primary and final.
Construction of 5 residential buildings in Ras Sadr
The project started on 5/28/2014 and ended on 9/28/2014. The duration of the project is 4 months.
Finishing - fully finished
Number of floors - 6 floors
Number of apartments - 24 apartments
Apartment area - 85 square meters
Delivery - The project was delivered initially and not delivered final, and the final payment and the final insurance were not paid
Finishing - fully finished
Number of floors - 6 floors
Number of apartments - 24 apartments
Apartment area - 85 square meters
Delivery - The project was delivered initially and not delivered final, and the final payment and the final insurance were not paid
A project to establish 3 schools in Buhaira Governorate
-
-
-
-
-
-
-
-
-
-
-
Construction of 5 residential buildings in Luxor
Duration: 10 months from 22/5/2014 to 21/3/2015.
Finishing: fully finished.
Housing type: above average.
Number of floors: 6 floors.
Number of apartments: 24 apartments.
Apartment area: 120 square meters.
Delivery: The initial project has been delivered, and its final delivery is underway.
Finishing: fully finished.
Housing type: above average.
Number of floors: 6 floors.
Number of apartments: 24 apartments.
Apartment area: 120 square meters.
Delivery: The initial project has been delivered, and its final delivery is underway.
Construction of 5 residential buildings in Highstep, first phase
Duration: 6 and a half months.
Finishing: fully finished.
Number of floors: 7 floors.
Number of apartments: 28 apartments.
Apartment area: 130 square meters.
Delivery: The project has been delivered primary and final.
Finishing: fully finished.
Number of floors: 7 floors.
Number of apartments: 28 apartments.
Apartment area: 130 square meters.
Delivery: The project has been delivered primary and final.
Construction of 5 residential buildings in Highstep, third phase
Duration: 6 months from 10/6/2015 to 1/1/2016.
Finishing: fully finished.
Housing type: above average.
Number of floors: 6 floors.
Number of apartments: 24 apartments.
Apartment area: 120 square meters.
Delivery: The initial project has been delivered, and its final delivery is underway.
Finishing: fully finished.
Housing type: above average.
Number of floors: 6 floors.
Number of apartments: 24 apartments.
Apartment area: 120 square meters.
Delivery: The initial project has been delivered, and its final delivery is underway.
Construction of 5 residential buildings in Al Tur
Duration: 3 months from 18/6/2014 to 28/9/2014.
Finishing: fully finished.
Number of floors: 6 floors.
Number of apartments: 24 apartments.
Apartment area: 130 square meters.
Delivery: The project has been delivered initially and has not been delivered final.
Finishing: fully finished.
Number of floors: 6 floors.
Number of apartments: 24 apartments.
Apartment area: 130 square meters.
Delivery: The project has been delivered initially and has not been delivered final.
Construction of 5 residential buildings in Burj Al Arab
Duration - 6 months, as the project started on 8/16/2014 and ended on 2/15/2015
Finishing - fully finished
The number of turns - 6 turns
Number of apartments - 24 apartments
Apartment area - 85 square meters
Delivery - it was delivered primary and not delivered final
Finishing - fully finished
The number of turns - 6 turns
Number of apartments - 24 apartments
Apartment area - 85 square meters
Delivery - it was delivered primary and not delivered final
Highstep 3 project, 2 residential buildings
Project duration: 3 months
Finishing: fully finished
Number of floors: 7 floors
Number of apartments: - 28 apartments
Apartment area: 120 square meters
Delivery: The project has been delivered primary and final
Finishing: fully finished
Number of floors: 7 floors
Number of apartments: - 28 apartments
Apartment area: 120 square meters
Delivery: The project has been delivered primary and final
Residential building construction project in Buhaira Governorate
Project duration: 11 months
Number of floors: 6 floors
Number of apartments: - 24 apartments
Apartment area: - 85 square meters
Delivery: The project has been delivered primary and final
Number of floors: 6 floors
Number of apartments: - 24 apartments
Apartment area: - 85 square meters
Delivery: The project has been delivered primary and final
Construction of 5 residential buildings in Highstep, second phase
Duration: 6 months.
Finishing: fully finished.
Number of floors: 7 floors.
Number of apartments: 28 apartments.
Apartment area: 130 square meters.
Delivery: The project has been delivered primary and final.
Finishing: fully finished.
Number of floors: 7 floors.
Number of apartments: 28 apartments.
Apartment area: 130 square meters.
Delivery: The project has been delivered primary and final.
Construction of 5 residential buildings in Ras Sadr
The project started on 5/28/2014 and ended on 9/28/2014. The duration of the project is 4 months.
Finishing - fully finished
Number of floors - 6 floors
Number of apartments - 24 apartments
Apartment area - 85 square meters
Delivery - The project was delivered initially and not delivered final, and the final payment and the final insurance were not paid
Finishing - fully finished
Number of floors - 6 floors
Number of apartments - 24 apartments
Apartment area - 85 square meters
Delivery - The project was delivered initially and not delivered final, and the final payment and the final insurance were not paid
A project to establish 3 schools in Buhaira Governorate
-
-
-
-
-
-
-
-
-
-
-
Construction of 5 residential buildings in Luxor
Duration: 10 months from 22/5/2014 to 21/3/2015.
Finishing: fully finished.
Housing type: above average.
Number of floors: 6 floors.
Number of apartments: 24 apartments.
Apartment area: 120 square meters.
Delivery: The initial project has been delivered, and its final delivery is underway.
Finishing: fully finished.
Housing type: above average.
Number of floors: 6 floors.
Number of apartments: 24 apartments.
Apartment area: 120 square meters.
Delivery: The initial project has been delivered, and its final delivery is underway.
Construction of 5 residential buildings in Highstep, first phase
Duration: 6 and a half months.
Finishing: fully finished.
Number of floors: 7 floors.
Number of apartments: 28 apartments.
Apartment area: 130 square meters.
Delivery: The project has been delivered primary and final.
Finishing: fully finished.
Number of floors: 7 floors.
Number of apartments: 28 apartments.
Apartment area: 130 square meters.
Delivery: The project has been delivered primary and final.
Construction of 5 residential buildings in Highstep, third phase
Duration: 10 months from 22/5/2014 to 21/3/2015.
Finishing: fully finished.
Housing type: above average.
Number of floors: 6 floors.
Number of apartments: 24 apartments.
Apartment area: 120 square meters.
Delivery: The initial project has been delivered, and its final delivery is underway.
Finishing: fully finished.
Housing type: above average.
Number of floors: 6 floors.
Number of apartments: 24 apartments.
Apartment area: 120 square meters.
Delivery: The initial project has been delivered, and its final delivery is underway.
Construction of 5 residential buildings in Al Tur
Duration: 3 months from 18/6/2014 to 28/9/2014.
Finishing: fully finished.
Number of floors: 6 floors.
Number of apartments: 24 apartments.
Apartment area: 130 square meters.
Delivery: The project has been delivered initially and has not been delivered final.
Finishing: fully finished.
Number of floors: 6 floors.
Number of apartments: 24 apartments.
Apartment area: 130 square meters.
Delivery: The project has been delivered initially and has not been delivered final.
Construction of 5 residential buildings in Burj Al Arab
Duration - 6 months, as the project started on 8/16/2014 and ended on 2/15/2015
Finishing - fully finished
The number of turns - 6 turns
Number of apartments - 24 apartments
Apartment area - 85 square meters
Delivery - it was delivered primary and not delivered final
Finishing - fully finished
The number of turns - 6 turns
Number of apartments - 24 apartments
Apartment area - 85 square meters
Delivery - it was delivered primary and not delivered final
Highstep 3 project, 2 residential buildings
Project duration: 3 months
Finishing: fully finished
Number of floors: 7 floors
Number of apartments: - 28 apartments
Apartment area: 120 square meters
Delivery: The project has been delivered primary and final
Finishing: fully finished
Number of floors: 7 floors
Number of apartments: - 28 apartments
Apartment area: 120 square meters
Delivery: The project has been delivered primary and final
(B) Projects belonging to the Ministry of the Interior
Sanabel Tower construction project - Nasr City
Duration: 2 years from 29/8/2012 to 28/8/2014.
Finishing: fully finished.
Number of floors: 11 floors.
Number of apartments: 47 apartments.
Apartment area: 250 square meters.
Delivery: The project has been delivered primary and final.
Finishing: fully finished.
Number of floors: 11 floors.
Number of apartments: 47 apartments.
Apartment area: 250 square meters.
Delivery: The project has been delivered primary and final.
(c) various projects
Construction of an administrative residential tower, Tahrir Street - real estate investment
-
-
-
-
-
Construction of 14 buildings in 6th of October City - Al Shams Housing and Development Company
It was not completed and was withdrawn.
The construction of the dream towers project
Location: next to Helmeyat Military Hospital, Helmeyat El Zaytoun Square, Cairo.
The project was sold (land + engineering drawings) to Al-Mariamiya Company
For Mr. / Amlika Abdo Luke.
The project was sold (land + engineering drawings) to Al-Mariamiya Company
For Mr. / Amlika Abdo Luke.
Construction of 2 towers next to Carrefour Maadi (Darna)
The Real Estate Company for National Banks purchased the land from Al-Saeed Contracting Company, and the company contracted with Al-Saeed Company as a contractor to construct the two towers, and the Real Estate Company for National Banks sold the units.